APPROVED
PLAN COMMISSION
April 3, 2008
Members Present: Ray Knapp, Chris Mueller (arrived 8:00 PM), David Wolf, Bob Rolle, Mark Mitchell, Paul Mahler
Members Absent: Dan Pearson (excused), Mark Mitchell (excused)
Staff Present: Rob Jones, Cedar Corp., Josh Miller, Cedar Corp.
Recording Secretary: Sharon Weide
Others present: Phyllis Albert, Josh Miller, John and Sharon Durbin, James and Heather Solie,
Jack Anacker, Glen Wiese, Marc Heintzman, Bill and Sara Poulos, Jocelyn Richardt, Teri Brosi, Gene Bahr, Corey Benedict, Charlie Macdonell, Greg Erickson, Jan Cuccia, LouAnn Endries, Theresa Barnes, Tammy Wittmer, Alex Blackburn, Michael J. Barnes; others were present who did not sign in.
Call to Order
Ray Knapp called the meeting of the Town of
AGENDA:
Minutes of the March 6 Plan Commission were
reviewed.
Paul Mahler
moved to approve the minutes of the March 6 Plan Commission meeting. David Wolf seconded. Motion passed, all in favor.
There were none.
Ray Knapp began by saying that the purpose of the
concept review is to complete the following tasks:
Cory Benedict introduced himself as the contractor
for Bill and Sara Poulos and stated that he would be managing the project with
the exception of any landscaping. Bill
Poulos went on to review the different aspects of the proposed project:
1. New house siding with stone
to be installed on the foundation,
2. Repair the deck, bring to
code by replacing some or all of the footings, move rearward about 2 feet,
3. Replace a railroad tie
retaining wall with rock and extend to the North side,
4. Install a pergola to make
the house more esthetically pleasing,
5. Repaint the garage and
install a new garage door.
Cory Benedict showed the Plan Commission a sample of
the siding and trim color, along with a picture of the rock proposed to be
used. Members agreed that the colors
were acceptable and that this portion of the project would be considered
ordinary repair and maintenance.
Ray Knapp then addressed the repair of the
deck. He began by saying that the
applicants may replace decking and railing within the scope of ordinary repair
and maintenance but that they would not be able to move the deck. Bob Rolle added that the Poulos’ would not be
able to replace the footings without a variance. Ray went on to say that because the deck is
classified as a nonconforming accessory structure it may not be structurally
altered, reconstructed, or expanded without a variance being issued. The Poulos’ stated that their intent was to
replace the footings in order to make the structure sound. Bob Rolle said that this would require the
Poulos’ to have the Ordinary High Water Mark (OHWM) determined and additional
documentation that will be reviewed later.
The next item discussed was the replacement of the
railroad tie retaining wall. Bob Rolle
felt that if only the existing ties were replaced that it could be considered
ordinary repair and maintenance. Ray
Knapp asked if a retaining wall would be considered an accessory structure, and
therefore non-conforming. Rob Jones said
yes, and that all, or significantly all of the structure could not be replaced. He went on to say that the wall could be
modified if it is necessary to address on-going erosion that a nonstructural
method could not address, if it would be constructed out of natural materials
and remain visually inconspicuous, and that the applicant submit detailed
construction, erosion control and vegetation management plans.
Sara Poulos asked if the size of the retaining wall
was not modified, just replaced would it be considered ordinary repair and
maintenance. There was additional
discussion around augmenting the existing retaining wall with stone and whether
there may or may not be footings or a welsh foundation under the existing
retaining wall. The Plan Commission was
not willing to commit to this at this time.
The Poulos’ need to provide additional information about this issue in
their application.
Bob Rolle explained that the pergola would not be
able to be built as expansion towards the river is not allowed. Finally, the painting of the garage to match
to house color and the replacement of the garage door would be considered
ordinary repair and maintenance.
Rob Jones then explained the application
process. He reviewed for the Plan
Commission the information that the applicants would be expected to provide
with the Riverway Permit Application.
These are:
1. A scale drawing showing all
pertinent information including setbacks and the OHWM
2. A recent aerial photograph
3. Proposed alterations of
vegetation and topography
4. A mitigation plan for
nonconforming structural expansion (if the retaining wall is to be extended)
5. Photos of the site taken
from the middle of the river, slightly upstream and downstream of the property
6. An erosion control plan
7. A vegetation management plan
8. Any other information
requested by the Town
1. A scale, or dimensioned,
drawing clearly showing the proposed decks within the footprint of the existing
decks.
2. Photographs clearly showing
the existing vegetation in the proposed areas construction.
9. Location of proposed on-site
wastewater treatment system and private water supply information
10. A plan showing the
proposed construction of structural erosion control measures and what is under
the existing railroad ties
11. Specifications for Transmission services
12. A construction plan for stairways and lifts
Bob Rolle
moved that the Plan Commission waive the requirement for Riverway Application
items 2, 9, 11, and 12. Paul Mahler seconded.
Motion passed, all in favor.
There was a short discussion with the Poulus’ on how
they might best proceed. Ray suggested
they look at recent riverway applications to see how to structure their
application. Ray Knapp then opened the
Public Hearing, Sara & Bill Poulos,
Jocelyn Richardt, Treasurer, Heartland Montessori
School explained that Heartland currently has two campuses, one in River Falls
that has a preschool and an elementary school, and one in Hudson (off of I94
and Exit 4) that has a preschool. Their
plan is to move the
Ray Knapp asked if any of the neighbors would like
to address the Planning Commission.
Jack Anacker,
Ray Knapp said that the Town could lower the speed
limit, without an engineering study, to 45 MPH, and to 35 MPH if an engineering
study is done. Mr. Anacker stated he
would like the speed brought down to 35 MPH.
Rob Jones said that the water and septic issue is a
County issue but there would definitely be an inspection by a plumber prior to
the special exception being granted.
Jocelyn Richardt stated that Heartland Montessori is non-profit and that
the property in
Jim Solie,
Sharon
Durbin,
Glen
Wiese asked if the old driveway off Coulee Trail is legal and if not would it
be closed off. Ray Knapp said it is not
a legal drive. Glen also requests that
there be hedging along the north side of the property and he would like to see
the playground in the front of the house.
He expressed concern about the septic system.
Members
of the Plan Commission asked Jocelyn for clarification on the following points:
1. Would there be meal service – No, the kitchen would
not be removed but no meals would be served.
2. How big is the play area, would it be fenced, where is
it located – 80 feet by 160 feet, fenced with a 5 foot green chain link fence. That design may change to include the
existing white rail fence. It will be located in the front, toward the side of
the house.
3. Could the play area be moved to the rear of the house
– No, because the rear of the house is the only area for the paved parking lot
as the septic system is in the front of the house
4. Will there be any other fencing and/or screening– A 6
foot Cedar fence on the west side of the yard is planned, there are a number of
evergreens and deciduous trees already on the property.
5. What type of signage – Heartland would like signage on
both Coulee and
6. Does Heartland plan to rent or buy this property – The
property will be purchased.
7. What type of lighting will there be – Heartland would
like 5 lights at the rear of the building that will remain on all night.
8. The number of student enrolled at the school –
Heartland plans for a maximum of 25 students, with a parent/toddler program
that would meet once a week for an hour and a half.
There
was considerable discussion around each of these points. Ray Knapp then asked each commission member
their thoughts on the proposed project.
Chris
Mueller felt that if the structure blends into the residential area he doesn’t
have a philosophical problem with it, although he feels the number of students
is high for the size of the house.
David
Wolf felt that he could support the project if it was done appropriately and
kept on a small scale.
Paul
Mahler also felt that the project needs to be scaled down; he did not feel that
the green chain link fence was aesthetically pleasing.
Ray
Knapp felt that the school could be a good use for the property but would like
to see the number of students limited.
Bob
Rolle felt he could support the project, but screening was important and he
would not support any signage on Coulee Trail.
He and Chris Mueller wanted to make it clear to the County that the Town
would be opposed to this project if strict conditions are not imposed in the
Special Exception.
After
considerable discussion on all of the above points the following recommendation
was made:
Bob Rolle moved the Plan Commission
recommend the Town Board recommend approval of County special
exception (institutional usage) –
1. there will
be no signs on Coulee Trail
2. the driveway
to Coulee Trail will be closed
3. there will
be vegetative screening on Coulee Trail
4. the play
area will be moved toward the back
5. there will
be no night time lighting other than what would be consistent in a residential
area
6. the white
fence will be left in front of the property
7. there will
be screening on the west side of the property that is acceptable to the
neighbors on the west.
8. there will
be no play equipment or hard surface south of the home
9. the property
will meet all state and government regulations for health, fire, insurance and
safety
10. there will
be no more than 25 students and no more than 8 students enrolled in the
parent/toddler program
11. the Town
would be extremely opposed to the County granting a special exception permit
unless these requirements are not mandated as part of the permit approval
process
Chris Mueller seconded. Motion passed, all in favor.
Rob Jones reviewed that the Walnut Hills subdivision
was constructed in accordance with revised plans that differed from the
approved plans referenced in the Developer’s Agreement. For that reason, the town has not yet
accepted the town roads within the subdivision.
The developer (Bright Keys) has met with Cedar corp. and
Rob then reviewed the developers proposed
resolutions to the storm water runoff problems.
The developer would clean the sediment out of the culvert at station
93+50, widen the area at the outfall to relocate the channel for erosion control,
providing rip-rap and fabric where needed, and reseed. They would build a drop rock stabilization
structure approximately 360’ from station 93+50 towards the pond. They would regrade the infiltration system
back from pond 4p to the drop structure.
The developer would remove an 8” PVC culvert between the ponds and
replace with an armored overflow (rip-rap and fabric) and reseed. They would remove sediments to the 952
contour in pond 4p and the 955 contour in pond 5p.
Ray Knapp asked how this would change the flow of
the water. Rob Jones explained that the
only way to lose water volume is to infiltrate it. The purpose of the above steps is to enlarge
the infiltration system to meet today’s standards. By increasing the infiltration water quality
is improved, volume is reduced and the rate is controlled. The proposed plans do not replace the two 36”
pipes with the 18” and 24” pipes in the original Developer’s Agreement.
Bob Rolle asked if the water wouldn’t run slower by
leaving the larger pipes in. Rob Jones
said that because the revised plan has more than doubled the storage and
provides for greater infiltration the water is changed, coming to the
pipes. This would be a better design
than the original. Ray asked if the
pipes could be screened. Rob said that
the Town could ask the developer to do so.
Ray Knapp then asked if anything was going to be
done with the holding ponds on the hill.
Rob explained that the holding ponds were only laid out for holding
water, not infiltration. Ray asked if
this had been discussed with the County as one of the objectives was to
infiltrate water. Rob thought that this
could be on the table as an objective.
Bob Rolle asked what was proposed for the developer
to insure that 5-10 years down the line the system doesn’t fail. Rob Jones stated that the County is looking
at requiring that the developer post a new letter of credit to insure that the
system is maintained, or to require that the homeowners association have a
maintenance plan written into the agreement.
Tammy Wittmer,
Ray Knapp asked about looking at the ponds at the
top of the site. Tammy thought that was
a reasonable request and said the Town and the County would need to identify
who’s going to be responsible for that and what the time frames would be. Ray then asked if smaller pipes to regulate
the flow could be installed at the upper pond.
Rob Jones said that putting in the smaller pipes would change the height
of the water, so that action would need to be reviewed. Rob also said that
infiltration systems on top could be a possibility, but that the soils would
need to be reviewed and new engineering would need to be done. Chris Mueller said that all the options
should be considered and if the solution reduces the size of the lots, then so
be it. Bob Rolle asked what was the biggest
failure at this site, Rob answered that it was erosion.
Ray Knapp asked the Plan Commission members if they agreed
with the following summary. The Town
would like to retrofit the up-stream ponds, deal with the increase in erosion
and sedimentation, clean the site of sediments, stabilize the site, and expand
the infiltration system and drop site.
The consensus was yes.
Gene Bahr, representative for Bright Keys, said that
the developer hopes to resolve these difficulties so that the project can be
completed. He stated he is willing to
work with the Town on a resolution.
Theresa Barns read a letter from she and Michael
Barns requesting the pipes to be changed from two 36” to 18” and 24” as
specified in the developer’s agreement.
That letter also addressed storm water runoff problems that have
occurred in the past and gave excerpts from County correspondence to the
developer and excerpts of discussions with the Town’s engineer. A copy of that letter is on file at the Town
Hall.
Phyllis Albert, who lives to the north, said that
she would like the runoff on the north side of the development reviewed as
there is a large waterway there and the potential for significant erosion once
the area is built out.
Ray Knapp then asked Rob and Tammy to clarify what
direction, from the Town, they are looking for.
Rob asked if the Town would be comfortable with another meeting taking
place between the Town, the County, the developer and an engineer of their
choosing. There was considerable
discussion on who should engineer the remainder of the project. Tammy Wittmer
expressed concern about getting a 3rd firm involved; she felt that
the system should be redesigned from the ground up.
Gen Bahr reiterated that he plans to work diligently
with all sides to get this completed.
Ray explained that the Plan Commission is required
by ordinance to make a recommendation to the Town Board if portions of the driveway
ordinance are clarified or modified. He,
Dan Pearson, and Gwen have been working on the ordinance. Ray used an outline from Gwen to work through
the areas that have been clarified.
First, Gwen suggested that the intent of the
ordinance had been to only regulate driveways that only enter onto Town roads
and recommend that the scope of the ordinance be clarified to address only
driveways that take access onto Town roads or private roads. The Plan Commission agreed to this.
Second, permits are reviewed and issued by the Town
chair “or designee”, currently the Town’s Building Inspector. Plan Commission advance approval is needed to
issue a driveway permit if the first building on the lot is not a house. The Plan Commission agreed to maintain this
procedure.
Third, the Town has the ability to inspect and
repair what are essentially private bridges or driveways over very large
culverts and do maintenance and repair if after notice the owner fails to
perform required maintenance. The cost
can then be charged back to all tax parcels using (or able to use) the private
structure as a special charge. The Plan
Commission agreed to this and added the verbiage “or Homeowners Association”.
Fourth, Section 125-6J was modified to further
clarify the location of field roads. The
Plan Commission agreed with this.
Fifth, Section 125-6I clarifies that only one
driveway is allowed per residential lot.
Bob Rolle said he would like to see the verbiage change to read
“Commercial lots and parcels greater than 20 acres in size may receive
additional driveway permit/s…”.The Plan Commission agreed with the intent of
these clarifying statements.
Finally, Sections 125-7 and 125-12 were modified to
clarify the process for removing a field road or driveway for which no permit
has been issued, at the owner’s expense.
The Plan Commission agreed with this modification.
Rob Jones reviewed several thoughts that Cedar Corporation
had about technical standards. The Plan
Commission agreed to add a maximum width for residential driveways based on
Rob’s comments.
Cedar Corp. also recommended replacing the text
description with a driveway profile diagram relating to driveway grade in the
appendix. The Plan Commission agreed to
revisit this at a later date.
Ray Knapp recapped the above items.
Chris Mueller
moved to recommend approval of the amended driveway ordinance with the changes
Ray Knapp has documented. Paul Mahler
seconded. Motion passed, all in favor.
Josh Miller, Cedar Corp, handed out the rewritten
Introduction, Setting, Methodology, and Recent Developments. He stated that some editing still needs to
take place. Bob Rolle also added that he
has 3 more paragraphs to be included. He
will forward those to Josh. The Plan
Commission decided that members will review the revised section and forward any
items for editing to Ray. He will
incorporate all of the edits into the document.
The Plan Commission then reviewed the revised
existing land use map. The map has
classifications for Residential, Commercial, Ag/Res and Exclusive Ag, along
with Riverway Zoning, and the Sending/Receiving areas from the Subdivision
Ordinance. Bob Rolle said that he would
like to see the Ag-res and Residential designations combined into one
color. The maps are still missing the
parks and conservancy designation and he would like to se that the TDRs sending
and receiving stand out more. After
discussion by the Commission it was decided to combine Ag-re and Residential
designations.
The Plan Commission then turned their attention to
what they would like to see on a future land use map. Bob Rolle would simply like to see the
addition of a commercial district along the Highway 35 corridor. He feels to get any more specific would carry
the weight of a zoning map and would break the deal previously made with the
farmers. Ray Knapp said that he would
like to see a future map that identifies large swaths of residential,
agricultural, and commercial development.
He feels that this would provide a vision of what the Town would like to
see in the future. Ray asked Rob Jones
for his input. Rob explained that
Menomonie’s future land use map had big bubbles that defined what their vision
was. Josh Miller said that in
After considerable discussion it was decided that
Bob Rolle would make a map up that would include a projected commercial zone
and Ray Knapp would make a map up that would have large swaths for the
differing zones.
Ray also suggested that there be special meetings to
discuss the Comprehensive Plan, rather than try to do it during a Planning
Commission meeting. The meetings will
take place on the last Thursdays of the month, with the first being April 24th
from 6 to 10 PM. These will be working
sessions only.
Ray Knapp explained that Jill Berke, Park Board
Chair, had asked that this item be tabled until the May meeting.
Paul Mahler
moved to table item 8 relating to the review & recommended land use
guidelines for parks. Bob Rolle
seconded. Motion passed, all in favor.
Building Permits were reviewed. There were no utility permits.
Ray Knapp said that he has been contacted by the DOT
to set up another meeting regarding Highway 35 with Bob Rolle, Dan Pearson and
himself attending, and is waiting to hear back on the date.
Chris Mueller
moved to adjourn the April 3, 2008 meeting of the Plan Commission at 11:58
PM. David Wolf seconded. Motion passed, all in favor