Call to Order 

Chair Berke called the meeting of the Town of Troy Park Board to order at 7:05 PM. 

 

1.      Adoption of Agenda

Member Small moved to adopt the agenda; second by Freund.  Motion was unanimously carried.

 

2.       Approval of Minutes

The minutes of the August 25, 2008 Park Board meeting were reviewed.  Member Freund moved to approve the minutes with minor corrections; second by Macdonell.  Motion unanimously carried.

 

3.      Confirmation by Town Board, Park Board Member #6, Suzanne Van Mele

The Town Board appointed Suzanne Van Mele as Park Board Member #6 at its most recent meeting.  Her term will expire July 31, 2012.

 

4.      Budget Review of Park Revenue/Expenditures for September; Approval of any Invoices

The park revenue and expenditures, through September 2009, as prepared by the Town Clerk and Member Macdonell, were reviewed.  Income in September was $1,077.80, and income to date was $7,995.90; expenses during September were $2,363.31, and expenses to date were $20,698.72.  There were no capital expenditures in September, capital expenditures to date were 6,933.16.  Member Small moved to approve the income and expenditures through September 2009 as tabulated by the Town Clerk, second by Member Freund.  Motion carried unanimously.

 

5.       Report of Park Impact Fees:

Impact fees available were $84,388.72 and County Park Funds were $94,461.50. 

 

6.       Review Constable Report – Mel Hermansen, Town Constable

¨       Cove Boat Ramp has been busy on weekends when the weather is warm, otherwise activity has been slow.

¨       Activity at Pembles has been very slow, as has Glover.

¨       Constable Hermansen walked all the trails at Glover August 21 and found no issues

   

 Enforcement Action Summary:

August 2009

Pemble’s Access

Cove Boat Ramp

Glover Park

Totals

Citations Issued:

0

7

0

7

Warnings Issued:

0

0

0

0

 

7.       Final Report, Eagle Scout Service Project – Bryce Dierke

Projects were completed (restaining the pavilion, installation of the trail kiosk near the south ball field) in August.  A total of six to eight Scouts assisted Bryce with the projects.  The total costs for the kiosk were $477.57 and for the stain were $162.49.

 

8.       Park & Recreation Reports

      Cove Boat Ramp

¨       Rip Rap and Ramp Repair Project:  No progress has been made by the Town Engineer (Cedar Corporation) since last month.

¨       There is continued evidence of power landing and launching.  There is sand buildup just beyond the ramp itself.  Signs may need to be added at the ramp next season indicating that power launching and landing are prohibited.

¨       Windmill Marina provided an estimate to store the town dock at their facility over the winter.  The estimate was $447.50 plus transportation.  Member Freund moved to accept Windmill’s estimate for boat dock storage, second by Small.  Motion carried unanimously.

 

Glover Park

a.                  Status Report, Playground equipment installation.  Installation has been scheduled for the week of October 5, 2009.  Equipment should be delivered to the park shortly before the installation will begin.

b.                  Status, updated park and trail map.  Chair Berke reported that the new trail map has been installed at the south kiosk.  The two remaining maps are in progress. 

c.                  Update Report hand pump and well.  Member Small reported that the pump was removed and repaired.  The pump appears to work well, taking 14-17 pump strokes to draw water.

d.                  Discussion, request to consider park closure during deer gun hunting season.  Historically, the park has been closed during the deer gun hunting season.  However, with development of residences surrounding the park, there is little deer hunting cover adjacent to the park.  The Board felt that because of this, closure of the park during the deer gun hunting season would not be necessary this year.

e.                  Update Report, Eagle project – Trail marking.  Member Small reported that most of the trail markers and intersection signs have been installed.  There are a few more signs that Thao is waiting to have printed, and he hopes to have the marking project complete in October.

f.                    Discussion, schedule inspection of ball fields and consider return of security deposit to teams.  The constables reported that the ball fields were generally being kept in good order by the ball organizations, with little trash or litter being left behind.  Member Macdonell moved to return the security deposits to the Hudson Boosters baseball organization and the River Falls Youth Baseball organization, second by Freund.  Motion carried unanimously.

 

      Pemble's Access

Activity Report

¨          Pemble’s is only open on weekends through September.  Very little use has been observed.

¨          Member VanMele will follow up with Darryl’s Septic to have the toilet removed from Pemble’s upon closing of the park for the season (October 1, 2009) and have the final invoice sent to the town.

 

10.  Discussion, status of TRIP local road improvement grants, N. Glover Road Project

North Glover Road is a designated bike route and is included as such in both county and state bike route maps.  Member Freund moved to support the Town Board’s efforts to secure additional grant funding to install the bike lanes on North Glover Road as part of the upcoming road reconstruction project, second by VanMele.  Motion carried unanimously.

 

11.  Discussion, Parks brochure

Chair Berke has explored the printing costs of a simple, letter-sized, one page brochure regarding Troy parks.  Estimates to print 400 brochures ranged from approximately $45-$140, depending upon color vs. black and white, specific paper selected, etc.  Berke will develop a draft brochure for Board review in the near future

 

12.  Review of 2009 budget

The 2009 budget was reviewed in detail using the spreadsheet prepared and maintained by member Macdonell.  Parks spending for 2009 are on budget.  Lawn Barbers submitted a proposal for lawn mowing and maintenance for the 2010 season.  Member Freund moved to approve payment in 2009 for 2010 lawn mowing for $10,225 less a 5% discount for payment this year, second by Small.  Motion carried 5-1.

 

 

 

13.  Preparation of 2010 budget

The Board reviewed the draft 2010 budget.  Several minor changes were made to the budget, Member Macdonell will revised the budget as discussed.  Member Freund moved to accept the budget as presented along with the changes discussed for presentation at the October 19, 2009 budget workshop with the Town Board, second by Small.  Motion carried unanimously.  Member Macdonell will update the spreadsheets and distribute them to the Park Board for further review and comment ahead of the budget workshop.

 

14.  Correspondence

None

 

15.  Announcements

None

 

Adjournment

Member Van Mele moved to adjourn the meeting, second by Freund.  Motion unanimously carried.  The September 22, 2009 meeting of the Town of Troy Park Board was adjourned at 10:20 PM.

 

 

Next Meeting:  October 27, 2009 7:00 PM at Troy Town Hall

 

Respectfully Submitted:

 

Gregory L. Small

Secretary